1928 Committee: Cupola Complete, Windows 80%, New Ductwork Approved; Sept. 23 Meeting And Site Tour Set

1928 Committee Moves Town Hall Renovation Forward: Cupola Complete, Windows Nearing Finish, Elevator Slips A Bit

The 1928 Committee moved briskly through approvals and progress reports at its latest meeting, closing with a unanimous decision to cancel the Sept. 9 session and meet on Sept. 23 at 4:30 p.m., followed by a hard-hat walk-through of the new Town Hall. 🛠️

Routine Business

  • Call to order and Pledge of Allegiance.
  • Minutes: July 20 minutes approved; one member noted an absence.
  • Correspondence: None.
  • Reports:
    • Chair: Work “moving along nicely,” with specific praise for the cupola and craftsmanship.
    • Town Council (Joe): Summer recess, “all quiet.”
    • FHS (Mr. Fagan): “Cruise control,” central office moving along; invoices approved as needed.

Design, FF&E, and Subcommittee Notes

  • The project is entering FF&E planning—furnishings, fixtures, equipment, and technology—with meetings expected within the next month or two so furniture installation aligns with building turnover.
  • Furniture will be a mix of new and existing items moved from the current Town Hall.
  • An interior design subcommittee previously met (Jack served). Membership and next steps will be clarified.

Construction Progress (KBE)

  • Cupola: Complete; scaffolding removed “as of yesterday.”
  • Windows: ~80% installed.
  • Cast Stone Replacement: Prep complete; stone en route; work in the next couple weeks.
  • Third Floor: Walls primed and first-coatedchair rails and window sills going in; ceiling grids to start soon, then progress downward.
  • Second Floor: Chair rails in; drywall surrounds at windows; ductwork in storage room.
  • First Floor (Gym): In-wall inspection passedinsulation going infloor inspection targeted for Friday to begin drywall.
  • New Addition: Steel and three lower roof areas complete.
  • Restrooms: New restroom forming passed inspectiondrywall hung.
  • Casework: Contractor installing corridor chair rails.
  • Windows Replacement Scope: “All” except several half-rounds.

Contractor coordination requests: Early notice for end-user requirements, FF&E deliveries, and elevator access for inspections once ceiling grids are in.

Elevator Timing

  • Original install target: Sept. 25.
  • Update received before the meeting: A delay of a couple of weeks is likely; the team has not yet accepted the push.
  • Recovery plan: Nights/weekends work to maintain overall schedule. In the meantime, stairs remain in service. 🧗

Financials, Contingency, and Change Orders

Budget & Contingency

  • Routine updates to line items and contingency logs.
  • Contingency used: ~46%.
  • Forecast of pending items: $68,333.31 (subject to change).
  • Contingency remaining (including forecast): $314,849.59.

Invoices Approved

  • Silver Petruzzelli (Architect): $23,077.78 for services through July 31.
  • IMTL (Materials Testing): $1,885 (reviewed by Mason).
  • J.I. Belluccio (Site Work): Two applications: $59,897.50 and $32,852.90.
  • KBE (Application #6): $1,718,911.59 (internally reviewed and architect-approved).

Change Orders Approved

  • Basement infills following boiler removal and prior ductwork abatement: $4,106.54.
  • Storm drainage increase (gym roof) from 4-inch to 6-inch: $8,000.
  • Arc-fault breaker (state fire marshal/vault requirement): $1,039.50.
  • HVAC ductwork—shift to all new system rather than mixed new/existing: $62,481.10.
    • Note: Multiple site meetings, calls, and reviews preceded this figure. The team emphasized better long-term value and elimination of testing/inspection complications on old fire dampers.
  • Dome substructure repairs discovered under the copper during removal; Elite rebuilt in ~2.5 days$11,514.88.
  • Handrails in stairwells retained and refinished rather than replaced: credit of $6,888.80.
  • Wall thickness increase to match conditions: $3,044.55.
  • Additional precast stone replacement (approximately 20 stones, largely under windows) to avoid future failures: $21,600.

Community Updates and Communications

  • Staff will prepare a photo-driven project update for the October Town Letter; a cupola shot is requested. 📸
  • Interior colors exist; finalization is “top secret” for now.
  • Cast stone swapping to begin “in a couple/three weeks.”

Next Meetings

  • Sept. 9: Canceled.
  • Sept. 23 at 4:30 p.m.: Regular business followed by a site tour of the new Town Hall. Hard hatsrecommended. Some members will be out of town; quorum expected.

Sponsor Note (Read with a grin)

This reporting is brought to you by Farmington Storage—the place you call when your basement finds out the cupola is done and demands its space back.
Address: 155 Scott Swamp Road, Farmington, CT • Phone: 860.777.4001 • Web: farmingtonstorage.com
They won’t install your elevator, but they will store your dignity while you take the stairs. 😎


About the Author

Jack Beckett drinks coffee the way ceilings take paint—first coat early, second coat before noon, punch-list by 3. If you see him near the cupola angle-hunting, he’s fine; he’s chasing daylight and an espresso.

Find more on our site: long-form explainers, committee indices, and practical guides—all without pop-up whack-a-mole. Browse our editorial work at Editorial, learn who we are at About The Farmington Mercury, and tag along with education, zoning, and HDC coverage: Farmington High SchoolZoningHistoric District Commission. Shopping? See For Sale. Jobs? Try Positions Available. Law-and-order reader? Visit Law Enforcement. Our wetlands are lively too: Wetlands Committee. Subscribe at The Farmington Mercury — Subscribe. Questions or news tips? Contact Us. And yes, you can always message us on X/Twitter (Twix) at @WeFarmington. 💬


Stay Informed with The Farmington Mercury

Subscribe for steady reporting on meetings, budgets, and decisions that shape the town—no tracking detours, no breathless hype. Start here: Subscribe.


After-Everything Links (because you asked nicely)


Creative Commons License

© 2025 The Farmington Mercury / Mercury Local
This article, “1928 Committee: Cupola Complete, Windows 80%, New Ductwork Approved; Sept. 23 Meeting And Site Tour Set,” by Jack Beckett is licensed under CC BY-ND 4.0.

“1928 Committee: Cupola Complete, Windows 80%, New Ductwork Approved; Sept. 23 Meeting And Site Tour Set”
by Jack BeckettThe Farmington Mercury (CC BY-ND 4.0)

Leave a Reply

Your email address will not be published. Required fields are marked *